Albury Paper Mill - NSW

A major upgrade of the Albury paper mill required removal of approximately 140 cubic meters of concrete to allow for the installation of a modern conveyor system. This project involved a very tight schedule that involved 12 Cut and Core operators working around the clock as other trades where scheduled to move into completed areas as soon as work was completed. A vast array of equipment was used including wire saws, hydraulic drills, deep cutting road saws and handheld cutting equipment.